Work site : Diyala province. Employer : Ministry of Municipalities and Public Works the Implementer : Al-Ezaa General Contracting Co. ltd (main contractor) cost of the project: 21.450.000.000 Iraqi dinars Cost of import materials: 3.000.000.000 Iraqi dinars amount of concrete: 12.000 cubic meters earthworks amount: 10.000 cubic meters Quantity of precast pillars: pillar 12:00 1843 length Duration of Contract: 2 years